Renovation project handover form
This document confirms receipt of the property and protects both sides
RBM · Handover form
A week before handover
- Walkthrough done without the client
- Every defect found has been fixed
- Defects not fixed have been explained to the client
- Handover date and time sent to the client in writing
- Warranty documents prepared
- Tile batch numbers recorded
System checks on handover day
- Electrics: every socket and switch checked
- Electrical panel: no tripping
- Taps: flow and sealing in order
- Drainage: checked for blockages
- Air conditioning: cooling and heating in order
- Doors: open and lock properly
- Cabinets and drawers: open properly
- Tiling: no broken tiles or flaws
- Paint: finished, no stains or gaps
Documents handed to the client
- Written warranty (start and end dates)
- Names and phone numbers of the main suppliers
- Tile batch numbers (for future repairs)
- Maintenance instructions (if relevant)
- Materials receipts / manufacturer warranty certificates
Meter readings on handover day
Open defects (to be handled after handover)
1.To be fixed by:
2.To be fixed by:
3.To be fixed by:
4.To be fixed by:
Note: no signature, no handover. If a client refuses to sign, find out why before you leave the site.
I, the undersigned (client), confirm
I received the property on in the condition recorded above. The listed defects will be handled by the dates stated.
Date:
Signature of the contractor who did the work
The property was handed over as agreed. I did a full handover walkthrough with the client and recorded the property's condition.
Date: